在matlab環境下,編寫的電力系統39節點系統,適合對電力系統進行潮流分析及相關方面的研究
代碼片段和文件信息
function?mpc?=?case39
%CASE39?Power?flow?data?for?39?bus?New?England?system.
%???Please?see?CASEFORMAT?for?details?on?the?case?file?format.
%
%???Data?taken?from?[1]?with?the?following?modifications/additions:
%
%???????-?renumbered?gen?buses?consecutively?(as?in?[2]?and?[4])
%???????-?added?Pmin?=?0?for?all?gens
%???????-?added?Qmin?Qmax?for?gens?at?31?&?39?(copied?from?gen?at?35)
%???????-?added?Vg?based?on?V?in?bus?data?(missing?for?bus?39)
%???????-?added?Vg?Pg?Pd?Qd?at?bus?39?from?[2]?(same?in?[4])
%???????-?added?Pmax?at?bus?39:?Pmax?=?Pg?+?100
%???????-?added?line?flow?limits?and?area?data?from?[4]
%???????-?added?voltage?limits?Vmax?=?1.06?Vmin?=?0.94
%???????-?added?identical?quadratic?generator?costs
%???????-?increased?Pmax?for?gen?at?bus?34?from?308?to?508
%?????????(assumed?typo?in?[1]?makes?initial?solved?case?feasible)
%???????-?re-solved?power?flow
%?
%???Notes:
%???????-?Bus?39?its?generator?and?2?connecting?lines?were?added
%?????????(by?authors?of?[1])?to?represent?the?interconnection?with
%?????????the?rest?of?the?eastern?interconnect?and?did?not?include
%?????????Vg?Pg?Qg?Pd?Qd?Pmin?Pmax?Qmin?or?Qmax.
%???????-?As?the?swing?bus?bus?31?did?not?include?and?Q?limits.
%???????-?The?voltages?etc?in?[1]?appear?to?be?quite?close?to?the
%?????????power?flow?solution?of?the?case?before?adding?bus?39?with
%?????????it‘s?generator?and?connecting?branches?though?the?solution
%?????????is?not?exact.
%???????-?Explicit?voltage?setpoints?for?gen?buses?are?not?given?so
%?????????they?are?taken?from?the?bus?data?however?this?results?in?two
%?????????binding?Q?limits?at?buses?34?&?37?so?the?corresponding
%?????????voltages?have?probably?deviated?from?their?original?setpoints.
%???????-?The?generator?locations?and?types?are?as?follows:
%???????????1???30??????hydro
%???????????2???31??????nuke01
%???????????3???32??????nuke02
%???????????4???33??????fossil02
%???????????5???34??????fossil01
%???????????6???35??????nuke03
%???????????7???36??????fossil04
%???????????8???37??????nuke04
%???????????9???38??????nuke05
%???????????10??39??????interconnection?to?rest?of?US/Canada
%
%???This?is?a?solved?power?flow?case?but?it?includes?the?following
%???violations:
%???????-?Pmax?violated?at?bus?31:?Pg?=?677.87?Pmax?=?646
%???????-?Qmin?violated?at?bus?37:?Qg?=?-1.37??Qmin?=?0
%
%???References:
%???[1]?G.?W.?Bills?et.al.?“On-Line?Stability?Analysis?Study“
%???????RP90-1?Report?for?the?Edison?Electric?Institute?October?12?1970
%???????pp.?1-20?-?1-35.
%???????prepared?by?E.?M.?Gulachenski?-?New?England?Electric?System
%???????????????????J.?M.?Undrill?????-?General?Electric?Co.
%???????“generally?representative?of?the?New?England?345?KV?system?but?is
%????????not?an?exact?or?complete?model?of?any?past?present?or?projected
%????????configuration?of?the?actual?New?England?345?KV?system.
%???[2]?M.?A.?Pai?Energy?Function?Analysis?for?Power?System?Stability
%???????Kluwer?Academic?Publishers?Boston?1989.